As of Jan 12th we are only allowed access on the property to be doing repairs. We are working on the rooms in the West Building replacing drywall, painting, ripping out carpet and laying tile. Concrete work on the corner of the East Building is awaiting a permit to be issued. Once this work is completed we will need another inspection before we can begin repairs on the ocean front units. We are facing numerous delays with supply chain issues, government regulations and permitting but are proceeding with plans to get our permanent seawall started before Turtle Season. Our staff is back onsite to facilitate repair work so owners please continue to use e-mail for communications. We appreciate your support.